Orora OT Network Latency in Packaging automation project for Packaging
Orora · Engineering Services

OT Network Latency in Packaging

At a glance
Industry
Packaging manufacturing
Platforms
Industrial Ethernet, OT network assessment
Scale
Production-critical OT network investigated while it kept running

Production-impacting latency traced to the OT network environment, with as-built schematics and recommendations to prevent repeat disruption.

Client
Orora
Sector
Packaging
Engagement
OT network latency investigation
Technologies
OT Network Assessment, Industrial Ethernet, Network Topology Analysis
Overview

Scope & approach

Packaging lines depend on timely communication between controllers, drives, HMIs and the machines around them, so network latency shows up as lost output rather than as an IT fault. Orora needed to understand excessive latency on a production-critical OT network where the disruption was already affecting output and the investigation had to proceed without taking the running network down. Metromotion Controls examined the network topology, device configurations and traffic behaviour to isolate where latency was being introduced, then captured the as-built environment in accurate Ethernet schematics. The work produced recommendations focused on restoring performance and reducing repeat disruption.

Outcomes

What was delivered

  • The investigation traced production-impacting latency back to the OT network environment through review of topology, device configuration and traffic behaviour.
  • Accurate as-built network schematics improved future troubleshooting and change control on site.
  • Recommendations were focused on restoring performance and reducing repeat disruption.
Deliverables

Scope items

  • Site investigation of OT network topology, device configurations and traffic behaviour
  • Development of accurate Ethernet network schematics reflecting the as-built environment
  • Recommendations report to reduce latency, improve network performance and prevent future production impact